An ageing ground mounted power transformer located in South Australia was scheduled to be removed from service and replaced. After the above-ground infrastructure was removed, transformer oil contamination was evident in the soil surrounding the footings.
Enviropacific Services was engaged to manage the excavation of the contaminated soil and to validate the pit as ‘decontaminated’ before it was backfilled with clean soil.
The hand-held RemScan instrument was used to measure Total Petroleum Hydrocarbon (TPH) levels in the soil during the site remediation and excavation process in real-time.
The levels of TPH in the worst affected areas were up to 100,000 mg/kg. The Enviropacific Services Project Manager directed the extent of excavation until the contamination levels in the walls and floor of the pit were below the target criteria of 1,000 mg/kg TPH as measured by RemScan.
The pit was then backfilled, and soil samples that had been collected from each of the pit walls and floor were sent to a NATA-accredited laboratory for independent validation.
A week later, the laboratory results confirmed the accuracy of the RemScan instrument measurements – all samples returned TPH values well below the target criteria.
Utilisation of the RemScan technology ensured that over-excavation and extra disposal fees were avoided, and provided the project team with the confidence that they could backfill the pit on the same day without having to return to site again.